← Back to news
August 4, 2026

Gov. Greg Abbott Pauses New Data Center Projects Amid Grid Audit

  • Governor Abbott orders an audit of pending data center projects seeking grid connections.
  • ERCOT confirms the directive effectively pauses all new data center projects.
  • The review will assess companies' electricity generation plans and resource usage.
  • Texas faces unprecedented electricity demand, with data centers accounting for 90% of new requests.

Read the news this way every day.

Concur organizes political reporting into clear stories and shows the sources behind each one.

Free. No ads.